Read below to discover more about the DeKalb County Surveyor's current projects:

  1. Erwin Selke Regulated Drain No. 439-00-0: As of the week of August 25, 2025, contractors have been on site removing trees and replacing tile as approved at the Hearing on August 7, 2025. Minutes from the hearing can be found below. Watershed members should have received a letter in the mail communicating the approximate on-site work dates. 
  2. Ora Bohler Regulated Drain No. 54-00-0: The DeKalb County Surveyor's Office and DeKalb County Drainage Board hosted a public meeting on August 5, 2025, for the purpose of gathering input from watershed members about a possible future reconstruction. To date, the DeKalb County Drainage Board has not approved a reconstruction project for the watershed. If the DeKalb County Surveyor or Drainage Board wishes to pursue a reconstruction, watershed members will receive a hearing notice in the mail 30-40 days before the hearing. Minutes and information from the hearing can be found below.